Tuesday 25 December 2018

Arten der Vorspannung



Arten der Vorspannung

Für die verschiedenen Anwendungsbereiche wurden verschiedene Methoden der Aufbringung der Vorspannung mit Spanngliedern entwickelt, die nach den Verbundeigenschaften der Spannglieder, dem Zeitpunkt der Aufbringung der Vorspannung auf die Spannglieder und der Lage der Spannglieder im Querschnitt unterschieden werden. die Bild gibt
einen Überblick über die heute gebräuchlichen Arten der Vorspannung mit Spanngliedern.




Referenz
Beton-Kalender 2017: Spannbeton, Spezialbetone.
Herausgegeben von Konrad Bergmeister, Frank Fingerloos und Johann-Dietrich Wörner


Tuesday 11 July 2017

INTRODUCTION IN SEISMIC

Seismic design 
Is primarily concerned with structural safety during major earthquakes, however the serviceability and the economic loss are also concern, depend on the size of the earthquake which the book divide them as follow:-
1-Minor → no damage
2-Moderate → some damage in nonstructural elements
3-Major→ some damage in structural elements
On the other hand, the distribution of forces and displacement resulting from earthquake influenced by three main factors:-
1-Properties of the structure
2-Properties of the foundation
3-The character of the earthquake it self
Building behavior 
The main idea is the inertial forces caused by vibration of the building mass are the main reason of building damages and the increase of the building mass may be has undesirable effects on earthquake design (F=m*a)
Where (m=building mass) (a=ground acceleration)
The magnitude of inertia force depends as we mentioned on:-
1-Building mass
2-The nature of foundation
3-Ground acceleration
Also the dynamic characteristics of the structure
So, 1-for the infinitely rigid buildings and it’s foundation it would have the same acceleration as the ground, in this case F=m*a
       2-for the buildings that deforms slightly it absorb some energy, in this case F<m*a
       3-for the tall buildings it’s more flexible than low rise buildings and much lower                                                                                        acceleration but it has much period that produce larger forces
Where (period=the length of a full cycle in second)
The magnitude of lateral force is not a function of the acceleration of the ground only, but also the response of the structure and its foundation and this relationship depends on the building period
The fundamental period for building is a function of its stiffness mass and damping characteristics and can vary from 0.05 to 0.30 times the number of stories
Influence of soil 
Harder soils and bedrock will transmit short-period vibrations and vice versa with softer soils, also the acceleration will be amplified if the fundamental period of the building coincides with the period of vibrations being transmitted through the soil, this amplified response called resonance
Damping 
Is the prevention of the building to oscillation and this depends on the building materials, connections and the effect of the nonstructural elements on the stiffness of the building, and the damping rations used in practice vary from 1% to 10% of critical damping
Where (critical damping=the minimum amount of damping necessary to prevent oscillation completely
Building drift
 In general is the total displacement of any point relative to the base, building joints must to permit adjoining buildings to respond independently to earthquake motion
Seismic design concept
1-select system that appropriate to the expected level of ground shaping, this include a redundant and continuous load path to ensure that the building responds as a unite
2-determining code forces and deformations
3-analys the building for the combined effects of gravity and seismic loads
4-providing details to assure the building has sufficient inelastic deformation ability to dissipate energy of the motion


Structural response to seismic
The resulting stresses and distortions in building are the same as if the base of the structure were to remain and horizontal forces are applied to the upper part of the building, these forces are the inertia forces equal F=m*a  where (m=w/g)
In general the building deforms in three dimensional manner (one vertical, two horizontal)
The inertia forces generated by the horizontal require greater consideration which the resistance to vertical seismic loads usually provided by the member capacities required for gravity loads
Load path
Seismic forces originated mostly in the heavy mass elements such as diaphragms, horizontal diaphragms distribute these forces to vertical force-resisting elements transfer the force into the foundation and the foundation transfer into soil
Irregularity
Typical building configuration deficiencies include an irregular geometry such as
1-A weakness story
2-Discontinuity in lateral system
3-A concentration of mass
These irregularities are defined in terms of strength, stiffness, geometry and mass and they can come with each other for example:- building that has a tall first story it has two of these terms (stiffness, strength)
Lateral loads resisting systems
1-Space frame resists the earthquake, the columns and beams act in bending, also this type has a large story drift but it may be accommodate without causing failure of columns or beams this system may be a poor economic risk unless special damage-control measure are taken
2-Shear wall system this more rigid than the previous, the story drift is relatively small, also it’s economical method to limit damage
This system excellent in these cases
1-Height to width ratio large enough to overturning problem
2-Soil is relatively soft
3-Dual system this when the frame alone can resist 25% of the lateral loads
4-Diaphragms this is the horizontal element (roof-floor) that distributed the lateral loads to the vertical structural elements
The diaphragms act like a deep beam, the floor is the web that carrying the shear and the wall is the flange of the beam that resisting the bending
The diaphragms must have the following:-
1-Resist bending and shear tied to act as one unite
2-To be adequate to transfer loads to lateral system
3-Openenig or reentrant must properly places and adequately reinforced
Ductility 
The capability to absorb energy with acceptable deformations without failure and it depend on the building materials, systems and reinforcing details
The ductility is measured by the hysteric behavior of critical component such as columns-beam assembly of moment frame (refer to figure 2.9)
Continues load path 
Or preferably more than on path with adequate strength and stiffness should be provided from the origin of the load ‘’inertia forces generated in an element’’ to the final lateral load resisting elements
Redundancy
Is a crucial characteristics for a good lateral performance and this means that the failure of a single connection or element doesn’t negatively affect the lateral stability of the structure 
Configuration
Building with irregular configuration won’t perform as well as a building with regular configuration even if it meet all code requirements
There are two types of irregularity:- 
1-Vertival irregularities 
2-Plan irregularities
For example, the building that take shapes (I, L, H, X) this is a plan irregularities and these shapes have two problems in seismic performance:-
1-Differential vibrations
2-Torsion because the not coincidences of the center of mass and the center of rigidity
We can solve these problems by tie the buildings together at lines of stress concentration and locate seismic resisting element at the extremity of wings or separate the building with joints with adequate width that allow the building to behave independently
Dynamic analysis
Static method based on single mode response while appropriate for simple regular structures
The dynamic analysis is preferred for design of buildings with unusual or irregular geometry
Symmetrical buildings with non-irregularity features behave in a fairly predictable manners, while the buildings that are asymmetrical or with irregularities don’t behave with predictable manners
For such buildings the dynamic analysis is used to determine response characteristics such as
1-Effect of the structure’s dynamic characteristics on the vertical distribution of lateral forces
2-The increase of dynamic loads
3-The effect of higher modes, resulting in an increase in story shears and deformations

SDOF-MDOF 
Simple oscillators are represented by single-degree-of-freedom system
Complex oscillators are represented by multi-degree-of-freedom system
SDOF the idealized system represent two kinds of structure
1-Single column with relatively large mass at its top
2-Single story frame with flexible columns and rigid beam
If the mass is deflected and then suddenly released, it will vibrate at a certain frequency that called fundamental frequency, the reciprocal of frequency is the period of vibration , it represent the time of the mass to move through one complete cycle, the period (T) is given by the following relation
T=2π*(M/K) ^0.5
Where (M=mass) (K=stiffness)
In an ideal system without damping the system will vibrate forever, but in the natural system and as the results of the damping effect the amplitude of the vibration will gradually decrease
The system will act in a similar manner if the instead of deflects the mass in the top, a sudden force hit the system to its base
MDOF the structure may be analyses as a multi degree of freedom by summing the story masses at intervals along the length of vertical pole
During the vibration each mass will behave differently, for higher modes of vibrations some masses may have in opposite directions or all masses may simultaneously deflect in the same direction as in the fundamental mode
The idealized of MDOF system has a number of modes equal a number of masses
When the ground motion is applied to a multi mass system, the deflects shape of the system is a combination of all mode shapes
For modes that have periods near predominated period of the motion will affect more than the other modes
Each mass presented by a single mass system having a generalized value (M) and (K), this values represent the equivalent combined effect of story masses and stiffness 


Building with irregularities is complicated not only the method of dynamic analysis, but also the method of combine the modes, so for building with regular and symmetrical shape, two dimensional model is sufficient
Note when the plan of the building aspect ratio (length/width) is large, torsion response may be predominate so it is required 3D analysis
For most building inelastic response can be expected to occur during a major earthquakes, that is mean that the inelastic analysis is more proper for design, but due to its difficulties and because it is expensive, in practice typically use linear procedures based on the response spectrum method

INTRODUCTION IN THE POST TENSION

Post tensionning
Types of prestressing
1-Post tensioning
The prestressing steel is either placed in a duct or sleeve before the concrete is cast
After the concrete is being casted and gained adequate strength, a stressing jack pulls the steel strands while reacting against the body of concrete member
Over time, a friction of the initial force in the concrete is lost due to creep and shrinkage of the concrete and relaxation of the steel

2-Pretensioning
The prestressing steel is first stressed and anchored against external bulkheads, concrete is then casted over the stressed steel
Once the concrete has developed adequate strength, the tendons are released from the bulkheads
The tendency of the stretched tendons to shorten pre-compresses the concrete

Advantages of post tensioned construction
1-Less steel
Using higher tensile strength of prestressing steel provides four and half times the capacity of the conventional steel 
The codes require a minimum amount of reinforcement in slabs to control shrinkage and temperature
The codes require a minimum amount of reinforcement to be distributed through the slab in both directions, so that the slab will have the necessary in plan strength for diaphragm action
The pre-compression imported by tendons spread rapidly through the slab from the anchorages and is sufficient to prevent cracking from shrinkage and temperature changes
The pre-compression provided by tendons under service condition is generally more than the minimum reinforcement required for diaphragm action, thus eliminating the requirement of adding reinforcement
2-Thnner slabs “less concrete”
Once span length exceed 5m, a post tensioned slab will be approximately one third thinner than the reinforced concrete slabs designed for the same loading
3-Large spans
Post tensioned slabs can span greater than conventional slabs of the same thickness 

4-Simple forms “eliminating of beams”
Application of post tensioning can allow beam to be eliminated, that will reduce the cost of forming as much as one-third of other system’s cost
5-Ability to better span irregular support arrangement
Post tensioned slabs don’t have to rely on the beam-and-slab framing common in conventional slabs, thus post tensioned slabs are particularly adaptable to irregular geometry
6-Lighter concrete forms “lower seismic demand”
The post tensioned concrete frame is generally one-third lighter than a conventionally reinforced
The supports and foundation tank the advantaged of the lighter floor system
7-Shorter concrete frames “reduce floor height”
Reducing slab thickness and elimination of beams results in shorter floor-to-floor height, and consequently, a reduction in the total height of the building
The shorter building have lower arm for the overturning moment created by seismic or wind
8-Greater ability to resist concentrated forces
The post tensioned acts as active load system, the applied force from post tensioning is generally configured to counteract the externally applied force, this reducing their undesirable effects
The tendons can be profiled to apply on upward force from that when combined with pre-compression from the tendons will counteract the applied force without undue deflection or need for local cracking
9-Reduce deflection
Post tensioning provides an upward force that balances a high friction of floor self-weight, thus reducing the net downward force that causes deflection
Post tensioned floors have greater flexure stiffness
10-Reduce cracks
Because the (ACI 318) imposes a low limit on the allowable tensile stresses, two way post tensioned floor slabs will be essentially crack-free under service conditions
When using the (EC2) the designer selects the extend of allowable cracking and a design crack width based on the anticipated in-service conditions of floor system
The designer choice becomes the amount of cracking and design crack width, as opposed to the elimination of cracking that results when using (ACI 318)
11-Improve resistance to water penetration
Because the post tensioned slabs have fewer cracks, thus provides a greater resistance to water penetration
12-Preception and acceptability of vibration
Foot fall on large areas supported on thin slabs can trigger unacceptable vibrations; cracking will exacerbate the problem because it lowers the natural frequency of the slab
Post tensioned slabs are generally thinner than their  conventionally reinforced counterparts and have longer spans, thus they are more prone to unacceptable vibrations
Two benefits of post tensioning help to reduce susceptibility of post tensioned floor to objectionable vibration
One is the reduction of weight (mass), the other is a larger relative stiffness because of less cracking, both features help to increase the natural frequency of vibration and improve the design
On the other hand, the longer spans used in post tensioned structure tend to lower the nature frequencies and aggravate the perception of vibration 
The vibration of post tensioned slabs under foot fall should generally be investigated where spans are relatively large

Application of post tensioning in building construction 
1-Floor system “flat slab construction”
a. Application in regions of high seismic risk, high wind forces
Because of lower weight and height and the improved of diaphragm action that results from pre-compression
b. General building applications
Optimum design in residential and commercial building flat slabs have spans between (8m to 10m)
2-Floor system “beam and slab construction”
When the aspect ratio of a slab panel exceeds two, it’s often more economical to use this system
3-Podium slabs in low rise building
For building up to five levels, post tensioned podium slab resists concentrated loads from posts and walls of the upper levels without requiring a support immediately below each load
Podium slabs are used in building which the lower level require a support layout that is different from the levels above
4-Transfer slabs
For high rise building where open space is required at the ground floor, one solution is to terminate the supports of upper levels on a transfer slab that received the loads from supports of super structure and transfer them to a limit number of generally widely spaced supports

5-Mat (raft) foundation
Post tensioned mat is used when the allowable bearing pressure is not adequate to resist peak stresses below walls and columns, but the total area of the soil below the foot print of structure is large enough to resist the total load
A well designed post tensioned mat can be as much as 40% thinner than a conventional reinforced concrete
6-Industrial ground support slab
In industrial storage areas, it’s necessary to provide a smooth ride for forklift and other loading equipment, a conventionally reinforced slab besides being subject to shrinkage cracks cannot accommodate the changes in the underlying soil with the flexibility of post tensioned alternative
Construction of post tensioned ground support slab
a) Covering the upper layer of underlying soil with two large of plastic sheets
b) The tendons are laid out
c) The concrete is casted
d) The tendons are stressed
7-Slab-on-grade “SOG for residential and light industrial”
SOG used to limit the effect of seasonal changes on building by limiting the shallow foundation movement
The objective is generally to limit the deformation in the structure to an amount that doesn’t impair it’s serviceability
8-Retrofit through external post tensioning
Post tensioning has been used effectively to correct strength and deflection deficiencies in building
When post tensioning is applied judiciously, its active force can configure the probable failure mode of structure, thus enhancing the structure’s level of safety
9-Post tensioning to restore geometry in seismic frames
In region of high seismic risk, building are designed to undergo post-elastic deformation, this helps dissipate the seismic energy and reduces the demand on resistance from the building frames
While building are designed to prevent collapse under anticipated seismic forces, they are expected to sustain damage
Observation from an earthquake revealed that multi story buildings that have experienced post-elastic deformation may not return to their original plumb position
Post tensioning can be used to restore a building closer to its original position after post elastic deformation from an earthquake
This is done by directing and controlling the post elastic deformation to designed location and using the force of prestressing tendons to restore the building to its original plumb position

10-Post tensioning in walls
When the lateral forces along the length of the wall are large and the vertical axial force is not adequate to prevent the wall from excessive tension, the wall possibly overturning
Post tensioning along the height of the wall in the vertical direction can be used to reduce tension and keep the wall in position
11-Post tensioning in column
When the column is subjected to significant bending, post tensioning reduces the axial capacity of the column

Post tensioning material and hardware
Types of post tensioning tendons systems
a. Unbonded
The prestressing steel is coated with a corrosion inhibiting grease, then encased in aplastic 

















Marking and recording of tendons position
Recording the as-installed location of the tendons is necessary to modify the structure in the future
This helps to identify where repair or drilling will require special precautions
A. Marking of tendons on finished floors
One way is to spray paint the location on the formwork before the concrete is cast, the paint mark will be transferred to slab soffit
Another option is to paint the tendons location on the slab soffit after removing the forms
B. Photo\video recording of reinforcement
Recording the position of reinforcement through photographs or videos and file the record as  part of the as-built documents of the construction 

Economics and material quantities
The economy of post tensioned slab versus a conventionally reinforced slab is a function of span length, the span of (7m) is the cross-over point between the two options
Compliance with different building codes and local practice can override the general case
When (ACI 318) is used for the design of column-supported floor system, a minimum amount of prestressing is required and spacing between tendons is limited 
These requirements do not exists in (EC2)
These and other requirements such as allowable stresses, mean that the design quantities are often a function of the building code
Engineering principles, local perception of good practice, can play a significant role in the quantities commonly used

1-Material quantities
A. Practice and project examples
The quantities consists of concrete, prestressing strands and non-prestressing reinforcement
The conversion to post tensioning reduce the total weight of reinforcement (combined PT and rebar ) by over 2.5 times
B. Base quantities for code compliance (ACI 318 AND EC2)
The quantities used in each construction derive from two requirements
i. First, the reinforcement to comply with the in-service and safety requirements for the applicable code
ii. Second, the reinforcement for structural detailing used for crack control at discontinuities 
C. Reinforcement for detailing
2-Construction cost
The bulk of the construction cost of a post tensioned floor consists of material, field labor, and equipment
A. Material cost
Cost of rebar, purchased, bent, and placed
Cost of prestressing material including hardware, placing, and stressing
B. Labor cost
The benefits of post tensioned structures includes
i. Less reinforcement, which results in lower labor cost for handling and placing
ii. Simplification in construction, which reduces the cost of labor for forming 
iii. Shorter construction cycle
The construction cycle is typically one week
This includes stripping and re-shoring the previously cast concrete, moving the forms to next pour and installing them, placing rebar and prestressing tendons, inspection, placing concrete, and stressing tendons3

Repair, Retrofit, Maintenance, and life cycle
1-Floors reinforced with grouted tendons
For slab with grouted tendons, the procedure for repair or remodeling are similar to conventionally reinforced slab
The prestressing steel is bonded to the concrete the same way that non-prestressing reinforcement is, but there are some important differences
I. At the strength limit state (USL), prestressing strand is capable of developing three to more than four times the force of non-prestressing reinforcement of the same cross-sectional area, thus cutting a prestressing strand can be more detrimental than cutting a rebar of comparable size if the design relies on the full strength of the cut strand.
As a result, the loss of effectiveness of the strand extends over a longer distance from the location of the cut
II. Bonded strand provides local precompression that is beneficial to crack mitigation, this precompression is lost if a section of the strand is removed 
The precompression from each strand is dispersed into the slab when the strand is stressed, once the tendon is grouted, the precompression is locked into the floor system
When the tendon is cut, there will be a local reduction in precompression, but the precompression imported from the remainder of the strand will remain
It is not necessary to re-stress and re-anchor a strand that has been cut, the grout that is injected into the duct, once hardened, locks the force into the tendon

2-Floors reinforced with unbonded tendons
When an unbonded strand is cut, it losses it force a long its entire length, thus its contribution to both serviceability and safety of the structure is completely lost
The cut tendon’s contribution to the precompression in the floor system will be lost over the entire length of the tendon
The loss of force and effectiveness of a tendon over its entire length require that the contribution of each tendon to be fully evaluated and, where necessary, compensated for the repair or retrofit
The repair/retrofit procedure generally consists of 
1. Exposing the affected tendons 
2. Carefully cutting them
3. Re-stressing tem and re-anchoring them at the face of the cut
The sequencing of the work may vary depending on the number of tendons need to be cut and the location of the new opening or the repair 
From the standpoint of a structure’s serviceability and safety, the loss of a single strand either inadvertently or by design, is usually not critical
Structural analysis for the effects of a lost tendon is often demonstrates that the structure has enough redundancy that it can lone one or more tendons without compromising its intended performance
If it is necessary to replace a lost strand, one option is to extract the damaged portion of the strand and rethread the sheathing with a smaller diameter, but higher strength
The new strand is coupled to the existing strand and the tendon is restressed



































Tuesday 24 November 2015

Autodesk university vs Autodesk academy







What The difference between the two AUTODESK official sites Autodesk university and Autodesk academy ?
Autodesk university mainly share separates lectures by famous Engineers , CEO or practitioners whose have alot of experience in a such software or even in concept or workflow and personally i considered this site is very useful site for those whose want to learn the concepts of work not the software tool only

Autodesk academy mainly share lessons, projects and curriculum to learn the software tool and also i consider it very useful site

AUTODESK SEEK

WHEN YOU WANT ANY FAMILY YOU CAN EASILY SEARCH IN THE OFFICIAL AUTODESK SITE (AUTODESK SEEK)
http://seek.autodesk.com/

Project Phases & Level of Detail (LOD)

Project Phases

In the construction industry, the design process is described by the phases of pre-design, conceptual design, design development, and final design. The building life cycle process is described by the phases of construction and building operation.
Typical Design Process of Buildings

Level of Detail (LOD)
In order to efficiently manage the process of working in a BIM workflow, the industry has adopted a formal language of describing the completeness of a digital model at a given point in time. This language is “Level of Development” (LOD).  LOD, in the BIM world, ranges from 100 (basic/conceptual) to 500 (highly detailed/precise). It is not unusual for levels of expected development to be part of the contract documents as described by the American Institute of Architect’s Building Information Modeling Protocol
LOD phases can be summarized as follows.
  • LOD 100:  Modeled elements are at a conceptual point of development. Information can be conveyed with massing forms, written narratives, and 2D symbols. 
  • LOD 200:  Modeled elements have approximate relationships to quantities, size, location, and orientation.  Some information may still be conveyed with written narratives.  
  • LOD 300:  Modeled elements are explained in terms of specific systems, quantities, size, shape, location, and orientation. 
  • LOD 400: Continuation of LOD 300 with enough information added to facilitate fabrication, assembly, and installation. 
  • LOD 500: Modeled elements are representative of as installed conditions and can be utilized for ongoing facilities management.
It is worth mentioning that a relationship between LOD and design phases can be loosely established. However, it should be emphasized this relationship is not empirical. For instance a project as a whole may be in design development, but in the digital model, the building envelope system may be fully detailed with exact materials and thicknesses. More so, plumbing systems might be represented with single lines, not modeled geometries.  


Reference :BPA certificate 

Monday 23 November 2015

WHAT IS NOT BIM ?

The term BIM is a popular buzzword used by software developers to describe the
capabilities that their products offer. As such, the defi nition of what constitutes
BIM technology is subject to variation and confusion. To deal with this confusion, it is useful to describe modeling solutions that
do not utilize BIM design
technology. These include tools that create the following kinds of models:
  • Models that contain 3D data only and no (or few) object attributes. These
are models that can only be used for graphic visualizations and have no
intelligence at the object level. They are fi ne for visualization but provide
little or no support for data integration and design analysis. An example is
Google’s SketchUp application which is excellent for rapid development
of building schematic designs, but limited use for any other type of analysis because it has no knowledge of the objects in the design other than
their geometry and appearance for visualization.

  • Models with no support of behavior. These are models that define objects
but cannot adjust their positioning or proportions because they do not
utilize parametric intelligence. This makes changes extremely labor intensive and provides no protection against creating inconsistent or inaccurate
views of the model.
  • Models that are composed of multiple 2D CAD reference files that must
be combined to defi ne the building. It is impossible to ensure that the
resulting 3D model will be feasible, consistent, countable, and display
intelligence with respect to the objects contained within it.
  • Models that allow changes to dimensions in one view that are not automatically refl ected in other views. This allows for errors in the model that
are very diffi cult to detect (similar to overriding a formula with a manual
entry in a spreadsheet).
REFERENCE BIM Handbook